In 2018, Newkirk Novak was awarded several packages of the Blue Springs R-IV School District bond issue. As a part of that work we are building a 2,500 square-foot addition high wind shelter with two classrooms at Chapel Lakes Elementary School. We began work on this project at the end of March this year and are expecting to finish by early August in order to avoid disruption to students during the school year.  

This week we made some very exciting progress and began work on the installation of a new roof, which we were able to complete in two days, as well as new brickwork on the exterior.